SystemTypical monthly unitsApprox. roof areaDetail
3 kW360300 sq ftSee the 3 kW page
5 kW600500 sq ftSee the 5 kW page
10 kW12001000 sq ftSee the 10 kW page
15 kW18001500 sq ftSee the 15 kW page
25 kW30002500 sq ftSee the 25 kW page

Typical figures are planning values derived from roughly four peak-sun-hours a day in Punjab, derated. They are not a guarantee of output.

Sizing

What actually decides the number

Six inputs, in roughly the order they matter. A size chosen without them is a budget decision wearing an engineering label.

  • How much you consume

    Twelve months of units where possible, not one bill. Roughly 120 units a month per kW is the planning figure everything else adjusts.

  • When you consume it

    A load that runs in daylight is offset directly. One that runs after sunset needs net metering to bank the surplus, or storage to carry it.

  • Usable roof area

    About 100 square feet of unshaded area per kW. Parapets, tanks, stairwells and neighbouring buildings all reduce what is genuinely usable.

  • Connection phase

    Single or three phase changes the inverter, the array arrangement, and how load is balanced across the installation.

  • What must survive an outage

    Backup is a separate question from size, and the answer drives the battery rather than the array. It is also where most of the cost variation lives.

  • The existing installation

    The board, protection and earthing decide what can be connected safely — and occasionally decide that remedial work comes first.

Bigger is not automatically better

An oversized array generates energy the site cannot use. Without net metering that surplus is simply lost, and with it the value depends on how the export is credited — which is decided by regulation rather than by the installer. Either way, capacity you never consume is capacity you paid for twice: once in equipment, once in the roof area it occupied.

Undersizing has the opposite failure. It trims a bill rather than changing it, and the second phase people plan to add later is more expensive than the capacity would have been at the outset, because the inverter, the cabling and the structure were all sized for the smaller system.

The honest middle is a size derived from twelve months of consumption, with the design leaving room for a defined expansion if one is genuinely likely. That is a decision to make before equipment is ordered, and it is one of the things a site survey settles.

Work out your size from your bill

Size your system

An engineer verifies the load and the site before any proposal.